On Saturday afternoon the air conditioning unit on the east side of SBC
stopped functioning. As you can imagine the temperature in all labs and
offices on increased rapidly without AC. The NMR consoles produce a
lot of heat and there are several components that are susceptible to
damage if this heat is not dissipated. Hence, I had to shut down both
Yosemite and BigSur consoles. The problem was still not fixed on Sunday
afternoon and the temperature in the room had reached 96 F, so I shut
down workstations to minimize heat in the room.
Hence there is no access to BigSur or Yosemite at the present time, nor
can you get data off of these instruments. If you need access to data,
please check the backup server. I do not know when these instruments
will be available, as the repair of the building AC is beyond my
control.
Kudos to Warren for calling me when the temperature of the room started
to rise or there could have been catastrophic damage to the consoles of
both 400s, the 800 and maybe even a mass spec.
Monday, July 30, 2012
500 w/cryoprobe in Malott
Siena (500 w/cryoprobe in Malott) will be unavailable on Monday August 6th until the morning of Wednesday August 8th because of annual service to the cryoprobe. We apologize for the interruption in service, however, in order to continue to acquire top quality spectra on this instrument, we must clean, replace, repair and/or service the many vital working parts of this instrument.
You can continue to submit samples for the cryoprobe both at Malott and SBC. Sarah and I will run them once the instrument is back up on Wednesday.
Please let me know if you have any questions or concerns.